The New Building
a | architect(s) | |
---|---|---|
18 | Firm | P&B Partner Architekten |
19 | Project Architect | Hochbauamt des Kantons Zürich (Building office of the Zurich Canton) |
20 | Type of project | (Rebuilding of an historical industrial building) |
b | aims of the new building | |
---|---|---|
21 | Short description of the main objectives and purposes of the project | Close the five old small library locations in Winterthur.
Provide new services for the students and the scientists. Extend the number of reader seats, workplaces and group rooms. Create a learning landscape with an activity-based conception of more than 1700 square meters. |
c | special features | |
---|---|---|
22 | Site | The new library is situated near by the Winterthur central station.
Currently the schools are in the distance from about 220 to about 800 meters to the library. |
23 | Architecture | 1. Rectangle plan of 100 x 16 m, complemented with a convex additional element of 100 x maximal 20 m, 20 m high.
2. Red Eternit (cement asbestos) shingles as historical built volumes today red shngles without cement asbestos of equal form, Curtainwall-construction. 3. House-in-house-construction 4. Reduced energy costs standard 5. Disabled access 6. Listed building |