Planning, preliminary brief
|
2003 - 2005 |
60 |
Architectural competition
|
No competition. Design Team procured 2005 through OJEU based of cost quality assessment |
61 |
Period of project
|
No |
62 |
Opening of the construction work
|
April 2007 |
63 |
Conclusion of the construction
|
April 2007 - January 2013, 7 sections |
64 |
Furnishing and moving the collections
|
Ongoing, with move management managed by Thomson Bethune. Major staff decants 2007-date. Two offsite stores created as part of project—one will be required permanently, one as decant store. |
65 |
Opening of the new building for public
|
Ongoing, first phase opened August 2008, Ground Floor opened June 2009. 7 floors now completed with Lower Ground Floor to be completed in January 2013 |