Costs (Including Taxes)
66 | Site | University owned. Site clearance and relocation of Security building £938,000 |
67 | Building | 27030400 euro [£20,653,000. Including AV (subject to agreement of final account)] |
68 | Furniture and equipment | 1417400 euro [£1,083,000] |
69 | Fees | £3,326,000 |
70 | Total | £26,000,000 (subject to agreement of final account) |
71 | Operating costs | £408,000 (staffing and maintenance per year) |
72 | Funding (Type of commission and source of funding) | University funded, with significant donations from alumni. |