Schedule Of The Building Process
59 | Planning, preliminary brief | New build library, with approximately 1000 study seats, with access to power and data, and 5000m of stock. |
60 | Architectural competition | Single stage competitive tender following OJEU procurement process. |
61 | Period of project | Autumn 2011 - May 2015 |
62 | Opening of the construction work | August 2013 |
63 | Conclusion of the construction | April 2015 |
64 | Furnishing and moving the collections | April 2015 - June 2015 |
65 | Opening of the new building for public | 27th May 2015 |