Schedule Of The Building Process

59 Planning, preliminary brief August 2003 - June 2009: 2 projets (2004-2005 and 2006-2009)
60 Architectural competition None, architects selected out of references
61 Period of project Thierry Algrin / Alain del Zotto
62 Opening of the construction work July, 5th 2010 (August, 16th 2010)
63 Conclusion of the construction foreseen: 26 to 28 months / in fact: 40 months (August 2010 - December 2013)
64 Furnishing and moving the collections BRUYNZEEL (shelves) ; SCHLAPPMOBEL (chairs, desks, shelves) ; YAMAKADO (tables) ; ARTEMIDE (light) ; RIVES et DICOSTANZO (movings)
65 Opening of the new building for public November, 15th 2013 (partial opening: November, 5th 2013)