Schedule Of The Building Process

59 Planning, preliminary brief planning started in September 2007, the construction in May 2010
60 Architectural competition In April - July 2007
61 Period of project July 2007 - Jan 2010
62 Opening of the construction work May 2010
63 Conclusion of the construction May 2010 - July 2012
64 Furnishing and moving the collections July - August 2012
65 Opening of the new building for public planned in Septembre - Novembre 2012