Schedule Of The Building Process

59 Planning, preliminary brief September 2007
60 Architectural competition October 2008
61 Period of project November 2009
62 Opening of the construction work May 2011
63 Conclusion of the construction ten months
64 Furnishing and moving the collections 31/01/12 - 14/2/12
65 Opening of the new building for public 15/2/12